Who this checklist is for
-
Step 1: Write the process spec before you talk to a single supplier
-
Step 2: Separate manufacturers from resellers
-
Step 3: Get the design scope in writing before you compare anything
-
Step 4: Build a TCO sheet, not a price comparison
-
Step 5: Match certifications to the actual service
-
Step 6: Plan installation before the equipment ships
-
Step 7: Lock down the documentation package
-
Common mistakes this checklist is designed to prevent
Who this checklist is for
If you're sourcing chemical process equipment for a new line, a replacement, or a capacity expansion, this list is for you. It's the same sequence I've used to manage roughly $2.3M in annual equipment spend across six years, and it's written for buyers who need to compare quotes on something other than unit price.
Seven steps. About 90 minutes of prep work, plus whatever your vendors take to respond. I've ordered them in the sequence that actually matters—spec before supplier, supplier before price, price before installation.
Step 1: Write the process spec before you talk to a single supplier
Most buyers ask for a quote first. That's backwards.
If you call a chemical process equipment manufacturer with "we need a heat exchanger, what's your price," you'll get a number that means nothing. It's not comparable to anyone else's number, and it probably assumes conditions that don't match your plant.
The spec is the input to chemical process equipment design. Before you solicit quotes, write down:
- Fluid or medium being handled, including concentration and impurities
- Flow rate range (minimum, normal, maximum)—not just one number
- Design pressure and design temperature, separately from operating values
- Corrosion allowance and material constraints
- Cleanability or sanitation requirements, if applicable
- Utility availability at the install point (steam pressure, cooling water temperature, power)
- Footprint and elevation limits
The question everyone asks is "what's your best price?" The question they should ask is "what's not in my spec that will change your price?" Nine times out of ten, the vendor will point to something you forgot—a design margin, a nozzle size, an NDE requirement—and that's the detail that separates a real quote from a placeholder.
Step 2: Separate manufacturers from resellers
Not every chemical process equipment supplier makes what they sell. Some are trading companies, some are system integrators, and some broker work to shops you'll never visit.
That's not automatically a problem—integrators can be useful for skid packages. But you need to know which one you're dealing with before you compare prices, because the risk profile is different.
Ask three questions:
- Where is the equipment fabricated? Get a city and a shop name.
- Who signs the pressure-boundary paperwork—an in-house engineer or a third party?
- Can we schedule a shop visit or a virtual FAT walk-through?
If the answers are vague, you're probably buying through a middle layer. Price accordingly.
Step 3: Get the design scope in writing before you compare anything
Chemical process equipment design is often bundled into the equipment price, and often it isn't. The difference can be 10-25% of the quote, and it's rarely obvious which one you're looking at.
Ask for a design scope document that states:
- Who produces the P&IDs, and who owns them at handover
- Who performs thermal and hydraulic calculations, and whether those are delivered to you
- Who selects materials of construction, and against which standard
- How many design review cycles are included, and what an extra cycle costs
- Whether the vendor participates in HAZOP or only supplies documents for it
I've seen a "free design" offer turn into $18,000 in change orders because the original scope stopped at preliminary sizing (surprise, surprise). Get it in writing. Simple.
Step 4: Build a TCO sheet, not a price comparison
This is the step where the checklist pays for itself.
Chemical process equipment installation commonly runs 15-30% of the equipment purchase price for skid-mounted packages, and higher for field-erected vessels. In our 2022-2024 project tracking, installation and commissioning averaged 18% on skids and 34% on field-erected columns—your site will differ, so build your own number, but budget for it.
Your TCO sheet should include, at minimum:
- Equipment price (with delivery terms: FOB, CIF, DDP)
- Design and documentation fees
- Freight, duties, and insurance
- Installation labor and rigging
- Foundation or structural modifications
- Utility tie-in (steam, cooling water, power, instrument air)
- Commissioning support and operator training
- Recommended spare parts (typically 3-5% of equipment value in year one)
- Warranty terms and the cost of an extended service agreement
The spreadsheet said go with the lowest quote. My gut said the one that took two weeks to answer a technical question was going to be slow everywhere else. I went with the mid-priced vendor. Later learned from a colleague at another plant that the low bidder had slipped a FAT by three weeks on a similar unit. Paid about 8% more upfront and never regretted it.
Step 5: Match certifications to the actual service
"We follow all applicable standards" is not a certification. Get the specific document.
For pressure vessels in the U.S., look for an ASME Boiler and Pressure Vessel Code Section VIII, Division 1 stamp—the "U" stamp for shop-built vessels (ASME, asme.org). Facilities handling regulated quantities of flammable or toxic materials fall under OSHA's Process Safety Management standard, 29 CFR 1910.119, and EPA's Risk Management Program under 40 CFR Part 68. Exporting pressure equipment to the EU requires CE marking under the Pressure Equipment Directive 2014/68/EU. Heat exchangers may be specified to TEMA class; pumps to API 610 if you're in refinery or petrochemical service.
Ask for the Certificate of Authorization number and the name of the authorized inspection agency. If a supplier can't produce them in 24 hours, they're either new to this category or not being straight with you.
Step 6: Plan installation before the equipment ships
This is the step most buyers skip, and it's the one that quietly doubles project costs.
Before the purchase order is cut, confirm:
- Floor or foundation load rating, and whether a structural review is required
- Utility connection sizes and locations at the install point—compare against the vendor's utility requirements drawing
- Rigging access: door widths, crane reach, overhead clearance
- Maintenance clearance for tube bundle pull, impeller removal, or internals access
- Lifting lugs and center-of-gravity data on the equipment drawing
I once watched a $90,000 skid sit in a laydown yard for nine days because the utility tie-in point was two feet off from where the vendor assumed it would be. The delay cost more than the field modification. Confirm these things on paper before fabrication starts.
Step 7: Lock down the documentation package
Never expected the mid-priced vendor to have the best documentation package. Turns out their design team was more thorough on as-built P&IDs than the premium bidder—and that package cut our maintenance troubleshooting time by hours per event over the next two years.
Contract for a documentation package that includes:
- As-built P&IDs and general arrangement drawings
- O&M manuals in your plant's language
- Material test reports and weld records
- Third-party inspection reports, where applicable
- Recommended spare parts list with part numbers
- Commissioning checklists and startup procedures
Put the document list in the purchase order as a line item with a delivery date. If it's not in the contract, you'll be chasing it for six months after the final payment clears.
Common mistakes this checklist is designed to prevent
Three things I still see on almost every bid tab:
Comparing unit price across suppliers. Two quotes for the "same" vessel can differ by 40% because one includes NDE, PWHT, and a U stamp and the other doesn't. Compare scope, not numbers.
Skipping the spare parts budget. Year-one spares typically run 3-5% of equipment value. Buyers who skip it pay expedite fees on the first failure.
Leaving the design scope ambiguous. If the contract doesn't say who owns the P&IDs and who pays for a second design cycle, you'll find out at the worst possible moment.
None of these require a technical background to prevent. They require asking the question before the PO is signed, which is the whole point of running a checklist in the first place.